Progress of work at the Świekatowo substation and GCP Koronowo
Construction of the technological building is underway at the Świekatowo substation:
- roofing work has been completed
- carpentry and electrical installations are underway inside the building
- the building’s facade is currently being constructed
At the 110 kV switching station, #AltergaTeam has completed the assembly of the structure and equipment, and now we are in the process of finalizing the busbar installation. Next, we will work on the secondary circuits.
In the case of the GCP Koronowo– on the existing substation in the newly constructed feeder bay, as well as at the Świekatowo substation – we are finalising the busbar installation after the assembly of the structure and equipment.
Thank you #AltergaTeam for the professionalism and excellent work!