2022-08-29 10:00 CEST

Reconstruction of the 110 kV power line Nałęczów-Klementowice, Klementowice-Puławy Rudy

Reconstruction of the 110 kV power line Nałęczów-Klementowice, Klementowice-Puławy Rudy

At the end of August 2022, Eltel Networks will start construction and assembly works consisting in the reconstruction of two 110 kV overhead power lines: Nałęczów-Klementowice and Klementowice-Puławy Rudy. We will start our activities with the installation of foundations near the existing foundations under an active power line.

The reconstruction of the 110 kV overhead power line Nałęczów-Klementowice, 11.17 km long, will involve the dismantling of the existing 41 stations with foundations, structures and cables, and then reassembly of new prefabricated foundations, earthing elements, EB24 pole structures, chains of composite insulators and cables .

The reconstruction of the 110 kV overhead power line Klementowice-Puławy Rudy, 8.04 km long, will involve the dismantling of the existing 30 stations with foundations, structures and cables, and then reassembly of new prefabricated foundations, earthing elements, construction of EB24 columns, chains of composite insulators and cables.

The investor is PGE Dystrybucja S.A. branch in Lublin.

Good luck and keep fingers crossed for our #ZałogaEltelNetworks brigades!