2024-10-04 13:00 CEST

News from the construction site of the Kruszwica – Karczyn power line

News from the construction site of the Kruszwica – Karczyn power line

We are pleased to announce that we are working at full speed on the construction of the Kruszwica – Karczyn overhead power line:

  • 3 out of 6 foundations are already in the ground
  • 5 poles have been screwed and are waiting for the switch off to be erected
  • the last pole in the allotment gardens is waiting for the switch off between 07.10-27.10.2024

According to the schedule, we are simultaneously carrying out construction works for the foundations on the Kruszwica – Mątwy overhead line. We already have 8 out of 23 planned foundations. The switching off of this line is planned for the period 19.11-19.12.2024.

We are continuing our work, keep your fingers crossed for a smooth implementation!