Substation Świekatowo and Main Supply Point (MSP) Koronowo

Substation Świekatowo and Main Supply Point (MSP) Koronowo

At the end of the previous year, construction work was completed at the Świekatowo substation, including the installation of external fencing and lighting. At the same time, partial levelling work was carried out.

In the technical building, #AltergaTeam carried out final works including:

  • installation of fibre optic cables
  • implementation of the SOT system
  • installation of batteries in the battery room
  • work in the transformer own needs rooms

In February, we are planning main commissioning stages at both the Świekatowo substation and the Koronowo Main Supply Point (MSP), covering the following systems:

  • telemechanics
  • security
  • other power infrastructure equipment

#AltergaTeam is consistently implementing the work schedule and preparing the power facilities for full operational readiness. We would like to thank the design and implementation teams for their professionalism and commitment.