We are building another GCP in Germany

We are building another GCP in Germany

At the end of last year in Germany, at the GCP (Grid Collection Point) station built by #AltergaTeam, we completed key stages of the investment related to the foundation and assembly of the main elements of the energy infrastructure:

  • we erected steel structures for 110 kV equipment
  • we laid the 30 kV cable route
  • we completed approximately 70% of the earthworks
  • the transformer, a key component of the GPO station, was installed

The planned scope of work was completed on schedule, allowing #AltergaTeam to smoothly move on to the next stage of work in the new year.

This is the result of the tremendous commitment and professionalism of our entire #AltergaTeam!