Summary of works on the 110 kV Kruszwica – Mątwy power line

At the end of last year, #AltergaTeam completed all work on the disconnection of the 110 kV Kruszwica – Mątwy overhead high voltage line. January 2025 was devoted to tidying up the area and settling the remaining tasks, in particular:
- cleaning up the area after work on the power line
- removing road slabs and tools from the construction site
- loading 3 long logs with containers
- delivering black earth to positions 78 and 79 (110 kV Kruszwica – Karczyn)
- cleaning up and loading pole positions
The next stage of implementation will be the completion of work on the 110 kV Pakość – Mątwy overhead high voltage line.
Thank you #AltergaTeam for your excellent performance and full commitment!